Chief Joseph Dam gets new turbine as feds replace aging hydropower technology nationwide

By Shannon Dininny, AP
Friday, May 28, 2010

Upgrades under way at Columbia River dams

BRIDGEPORT, Wash. — Workers are preparing to install a new 45-ton turbine at the second-largest hydropower producing dam in the United States, part of a multiyear upgrade that will generate power for an additional 30,000 Northwest homes.

The $120 million project at Chief Joseph Dam on the Columbia River is one of several planned around the country as the federal agencies that operate hydropower dams replace aging equipment and employ new technology to produce more power from the same amount of water.

In the Northwest, about 40 percent of the region’s low-cost electricity comes from hydropower dams, many of which were built decades ago and require upgrades.

The region also is home to the largest power-producing dam in the country — Grand Coulee Dam — where work is wrapping up to replace 18 turbines. Ten new turbines are to be installed downstream at Chief Joseph Dam by 2014.

Chief Joseph Dam already supplies enough power for the city of Seattle. Between both dams, the new turbines will produce enough power for an additional 60,000 homes once they are fully operating.

These massive hydropower projects are key to integrating an increasing renewable energy supply, such as wind power, into the electric grid, said Mark Jones, manager of federal hydropower projects for the Bonneville Power Administration, the federal agency that sells electricity wholesale to public utilities in the region.

The frequent starts and stops of intermittent wind power can stress the electric grid, but hydropower can be dialed back to offset those stresses more easily than some other power sources, such as a nuclear or coal plant.

The 31 dams in the Columbia River system also offset carbon dioxide emissions equivalent to 20 coal plants, Jones said.

BPA is evaluating smaller projects that could improve reliability and efficiency in the power supply. Electricity ratepayers fund all the projects.

“Most of what we spend money on is to just try to maintain the system for the next generation. By maintaining the aging infrastructure, investing in reliable upgrades, we continue to be able to produce reliable, low-cost power for the region,” Jones said. “And everywhere we can, we try to gain new efficiencies.”

The number of aging hydropower dams in the United States means an increasing need for new turbines to replace aging equipment, said Claude Lambert, vice president of Alstom Hydro North America, a Montreal-based company that produced the new turbine runner measuring 8 feet high and 16 feet in diameter.

“We foresee an increase in the coming years, but it will also depend on the economy of the country, whether there will be financing to do the projects,” Lambert said.

The U.S. government manages more than 1,000 dams nationally between the Bureau of Reclamation and the Army Corps of Engineers. In March, the Energy and Interior departments and Army Corps of Engineers signed a memorandum of understanding to focus on increasing energy generation at hydropower dams and explore opportunities for new developments.